Open panel is a system which drastically resolved problems with hanger conventional metallic ceiling finishing materials such as structural instability in method of connection, difficulty in maintenance and repair. visual problems due to exposure of fixing screws and lack of resistance against vibration under the condition of continuous vibration etc. It has functional excellence, convenience for works and applicability for diverse design thus it is universal ceiling metallic finishing material for which can be applied to all types of canopies such as those for commercial and office buildings, pilotti parts of residential buildings and metallic ceilings for railways/subways.
Outline of open panel for subway (Al, Steel, incombustible)
Open panel is a system which drastically resolved problems with hanger conventional metallic ceiling finishing materials such as structural instability in method of connection, difficulty in maintenance and repair. visual problems due to exposure of fixing screws and lack of resistance against vibration under the condition of continuous vibration etc. It has functional excellence, convenience for works and applicability for diverse design thus it is universal ceiling metallic finishing material for which can be applied to all types of canopies such as those for commercial and office buildings, pilotti parts of residential buildings and metallic ceilings for railways/subways.
Composition of open panel for subwayss (Al, Steel, Incombustible)
(1) Materials
KSD 3506 (melt galvanized steel plate) KSD 3609 (Steel material support for member for construction)
(2) Dimension
① ST'L MAIN T-BAR : 25X38X0.4T (L=3600)
② ST'L CROSS T-BAR : 25X25X0.4T
③ HANGER BOLT : 9mm X 1,000
④ HANGER & PIN : 105X20X2.0T
⑤ CARRYING CHANNEL : 38X12X1.2T
⑥ C/C JOINT : 100X35X10X1.0T
⑦ C/T clip (for St'l T-bar)
⑧ MINOR CHANNEL : 19X10X1.2T
⑨ M/C CLIP : 38X23X14X1.2T
⑩ HANGER NUT : ψ9
⑪ Molding (for open panel, for T-bar)
⑫ Open panel :590 x 1190 x 0.8T
Special feature of Open Panel for Subwayy (Al, Steel, incombustible)
* Screw is concealed thus exterior is beautiful.
* Excellent against vibration and quake-proofness
* Individual attachment and detachment are possible and no need for inspection hole.
* Possible for forming diverse plane.
(1) Setting up centerline of building: After accurate measurement of ceiling surface set up centerline after checking other work schedule such as lightline and position of diffuser etc.
(2) Strong anchor work
① At the time of strong anchor work when centerline is set up mark part for fixing strong anchor (Ф9mm) at slab surface and punch hole with drill and fix it.
② At the time of work for cash iron insert (Ф9 mm) install it at form according to drawing.
③ Caution: Pay attention to intervals between anchor and insert and right angle.
④ It is ideal to make interval for installation as @900∼ 1,200 mm for strong anchor or insert in consideration of direction of installation of carrying channel.
(3) Molding line level check
① Use of water level or level
a. Confirming position by means of drawing (confirming height of ceiling)
b. Confirming the position by water level and ink pot string marking between positions.
② Caution: At the time of using water check make sure to check level after checking any presence of air bubble in hose and breaking of hose.
(4) Attachment of wall molding (using after painting angle or seagull type molding)
① Attach molding along the India ink line and fix wall molding by using 1" concrete nail. (interval: 500∼1,000 mm)
② Be careful not to slacken the height and interval between moldings.
③ In connection with facilities such as curtain box it shall be attached according to specification.
(5) Installation of hanger bolt
① Upper part of hanger bolt is fixed to strong anchor or insert and lower part of bolt is fixed hanger and nut in consideration of ceiling height.
② At the place where installation duct or other obstacles are work shall be carried out after reinforcement according to drawing and specification.
(6) Installation of lightline
Install lightline according to specification but it is required to have consultation with persons in charge of electricity and facility.
(7) Installation of carrying channel
After tying hanger set and carrying channel and fix them. Install it at an interval of @900∼1,200 mm. Connect the connecting part of carrying channel by means of carrying joint.
And make sure to install carrying channel not to be off from box face by more than 30 cm.
(8) Installation of MINOR Channel
When area of work is broad reinforce and fix above the installed carrying channel with reinforcing channel (minor channel) and install it at an interval of 2,000 ∼3,000 mm.
(9) Installation of Main and Cross St'l T-bar
① After placing string at centerline of the work then install Main St'l T-Bar by using C/T Clip by matching it to lightline and in a right angle direction toward carrying channel.
② Intervals of installation: It shall be installed in general with an interval of @600 mm ot otherwise be installed according to size of panels.
③ It shall be installed by inserting cross st'l bar tip to groove of main st'l T-bar. (interval of groove :@150 mm).
④ At the time of installation of cross st'l bar groove of main st'l bar shall match to groove of other main st'l bar.
(10) Installation of finishing plate (open panel)
① Level of installed ceiling frame is accurately set by water level or level device.
② After completion of main and cross st'l T-bar connect design open panel to main st'l T-bar in level.
③ Prohibit use of plate with scratch, with dirt, distortion or damage.
(11) Installation of curtain box
① Manufacturing and installing products suitable to use according to specification (separate painting)
② Welding work is carried out concurrently therefore install work bench to enable safety in work and working in comfortable stance.
(1) Handling and storage of the product
① It shall be stored at a condition of relative humidity of 80% or less.
② To prevent any damage from water or moisture always keep it at dry and clean place.
③ Be careful not to damage corners
④ Maintain certain space from the wall surface and place spread sheet and then lay down water-proof sheet then preserve it.
(2) Environmental condition at the time of carrying out the works
① At the time of works temperature of 30℃ or less and relative humidity of 80% or less shall be maintained.
② The works shall be commenced after completion of joiners' works.
③ Before. during and after the works air-conditioners shall be operated so that proper level of indoors temperature and relative humidity are maintained.
④ The works shall be commenced after completion of all the papering and painting walls and ceiling.
(3) Caution at the time of carrying out works
① Pipe-laying and electric works shall be completed before installation of ST'L T-bar and then works shall be carried out.
② Check the connection of open panel and ST'L T-bar.
(4) Conditions for carrying out works
① The contractor for the works shall consult with the client with sufficient consideration of site conditions.
② While carrying out works at the time of appearance of any problems works shall be continued after sufficient consultation with the client.
③ As much as possible ceiling plan intended by the designer shall be observed.